Architectural
1 Physical development planning:-
· the national physical development plan
· regional physical development plans
· district physical development plans
· Urban physical development plans
· Local physical development plans
Stages |
Report / Document |
1. Feasibility planning Stage |
·Inception report/conceptual Masterplan |
2. The preliminary Stage and report |
· Zoning Layout plan/draft Masterplan |
3. Scheme design stage & Report |
· Draft Detailed Masterplan |
4. Final Design Stage Report |
· Detailed Master Plan & Report · EIA-report |
Phase i Design and specifications
Stage 1 Feasibility planning/site investigations
Stage 2 Preliminary (Outline) design
Stage 3 Scheme designs (working drawings)
Stage 4 Detailed Designs, Bills of Quantities and Tender Documentation
Phase ii Technical Assistance during Tender Action
Phase iii Construction supervision and Project Management
Stage 1 Construction Supervision
Stage 2 Defects Liability Period
The methodology adopted, tasks and activities to be done in each stage are outlined below.
Phase i: Design and Specifications
a) Mobilization
· Staff Mobilization
· Obtain Client Brief
· Attend Briefing Meeting
· Design Team Meetings
b) Stage 1 – Feasibility Planning
· Needs Assessment
· Site Surveys and Investigations
· Conceptual Designs and Feasibility Report
· Obtain approval from the Client for the concept designs
c) Stage 2 – Preliminary (Outline) Design Stage
· Develop a design brief
· Prepare preliminary (outline) design drawings
· Prepare/submit a preliminary design report
· Obtain approval from the Client for the preliminary (outline) designs
d) Stage 3 -Scheme Design Stage
· Scheme design drawing
· Scheme design report
· Obtain approval from the Client for the scheme designs
e) Stage 4 – Detailed Design Stage
· Final design drawings
· Technical specifications (architectural, engineering & services)
· Obtain approval from the Client for the detailed designs
· Bills of quantities & Confidential Cost Estimates
· Tender Documents
Phase ii: Technical Assistance during Tender Action
· Prequalification of Contractors
· Tender Action
· Evaluation Report
· Contract Signing
Phase iii: Construction supervision and Project Management
a) Construction Supervision
· Site Handover
· Mobilization
· Performance bond
· Advance payment guarantee
· Work program approval
· Commencement order
· Project management charter
· Insurance for the works
· Site Meetings
· Construction records
· Monthly Progress Reports
· Checking of line and levels
· Interim payments
· Complaints
· Certificate of Practical completion
b) Post Construction Stage
· Site Inspections
· Defects liability supervision
· Retention money
· As-Built Drawings
· Dispute resolution